BUSINESS

How to Price Construction Retainage

Contractor method for calculating how much a retainage clause holds back from each payment.

Retainage is a percentage the client holds back from each draw to protect against incomplete work. The risk is that it quietly ties up cash flow, so price it and plan for it before the contract is signed.

THE SHORT ANSWER

How do you calculate construction retainage?

Multiply the amount billed to date by the retainage percentage. On a fully billed $250,000 contract at 10%, $25,000 accrues; if the contract releases half at substantial completion, $12,500 remains held.

01

Read the contract clause

Retainage rates differ by project and sector. Ten percent is common on commercial work, and many public and private clients hold it until substantial completion.

  • Confirm the percentage
  • Check when it releases
  • Note any half-release milestone
02

Multiply the contract value

For a $250,000 contract at 10%, the total retainage is $25,000. The amount actually withheld rises with the billed portion, not the whole contract up front.

03

Apply the release schedule

If the fully billed contract releases half at substantial completion, the amount still held falls to $12,500. The remaining half releases under the contract's final-acceptance terms.

04

Plan cash flow around it

The retained balance is money you have already earned but cannot collect. Build it into your payment schedule and cover it with working capital or a clear drawdown plan. Use the Construction Retainage Calculator to see the numbers.

TRY THE TOOL

JOB INPUTS

Enter your numbers

Loading saved values

Total contract value

$
Total contract value

Percent the client holds back

%
Percent the client holds back

Share of the contract billed so far

%
Share of the contract billed so far

Release half when the job is substantially complete

Release half when the job is substantially complete
Results update automatically
CALCULATED RESULTUSD
Retainage currently held$12,500.00
Total retainage (project end)$25,000.00
Billed amount$250,000.00
Net received so far$237,500.00
FORMULA USED$250,000.00 × 10.0% = $25,000.00 → half released: $12,500.00
NEXT STEP

Turn the checklist into real job numbers.

Open contractor tools