HOW TO USE IT
How to use the Construction Crew Productivity Calculator
- 1
Set a realistic production rate: Start with the area one person can produce per hour in the trade and conditions. Confirm it for the actual crew, not an industry average.
- 2
Count man-hours, not crew hours: Man-hours are the crew size times hours worked. A 3-person crew over 8 hours is 24 man-hours, which is the basis for output and cost.
- 3
Multiply to the daily output: Output is the production rate times the man-hours. A 150 sq ft/hr rate over 24 man-hours is 3,600 sq ft, a useful daily target.
- 4
Use output to check the bid: Compare the computed output against the crew's actual pace. If the estimate assumes more than the crew can do, the bid is at risk. Use the Construction Crew Productivity Calculator.
THE MATH
Crew productivity calculation method
Multiply the production rate per person per hour by the crew size and hours. A rate of 150 sq ft/hr/person with 3 workers over 8 hours is 24 man-hours and 3,600 sq ft of output.Man-hours are the crew size times hours worked. A 3-person crew over 8 hours is 24 man-hours, which is the basis for output and cost.
PRACTICAL EXAMPLE
Worked example for Crew productivity
Multiply the production rate per person per hour by the crew size and hours. A rate of 150 sq ft/hr/person with 3 workers over 8 hours is 24 man-hours and 3,600 sq ft of output.
FAQ
Frequently asked questions
How do you estimate crew productivity?
Multiply the production rate per person per hour by the crew size and hours. A rate of 150 sq ft/hr/person with 3 workers over 8 hours is 24 man-hours and 3,600 sq ft of output.
What should I verify before using the result?
Bid with the pace the crew can actually hold, then track it to improve next time.
Is this a final quote or design?
No. Use it as a planning estimate, then confirm measurements, local rates, product requirements, permits and jobsite conditions before bidding or building.